Item | Amount |
Fundraising Goal | $5,000,000 |
Amount Raised To Date (as of 08/12/2020) | $3,300,000 |
Amount Remaining To Be Raised | $1,700,000 |
Note: The original estimate of $3 million for the renovation was raised to $5 million. Additional infrastructure requirements, new city code requirements, modifications to the original architectural plan, and higher construction and material costs all contributed to this increase.
Pending and Completed Tasks
Task/Subject | Last Update | Completed |
Notes |
Resubmit all information to City of Fremont | In progress | ||
Update Landscape Architecture drawings and response to comments | In progress | ||
Update Architectural drawings and responses to City’s comments | In progress | ||
Survey to combine 2 lots | 07/13/2021 | Survey by Bay Area Land Surveying Inc.
Scope of the work: 1. Lot merger |
|
Air Quality and Noise Update | 11/10/2020 | Illingworth&Rodkin, inc | |
Parking Analysis | 09/18/2020 | Complete | |
Arborist Report Update | 08/01/2020 | Complete | |
Historical Review Studies | 07/06/2020 | Complete | |
Civil Engineer to complete all responses for resubmit | 05/04/2020 | Complete | |
Traffic Studies | 08/02/2019 | Complete | |
Submit formal permit application to City of Fremont | 06/26/2019 |