Item Amount
Fundraising Goal $5,000,000
Amount Raised To Date (as of 08/12/2020) $3,300,000
Amount Remaining To Be Raised $1,700,000

Note: The original estimate of $3 million for the renovation was raised to $5 million. Additional infrastructure requirements, new city code requirements, modifications to the original architectural plan, and higher construction and material costs all contributed to this increase.

 

Pending and Completed Tasks

Task/Subject Last Update Completed

Notes

Resubmit all information to City of Fremont In progress
Update Landscape Architecture drawings and response to comments In progress
Update Architectural drawings and responses to City’s comments In progress
Survey to combine 2 lots 07/13/2021 Survey by Bay Area Land Surveying Inc.

Scope of the work:

1. Lot merger
2. Right of way dedication along the project frontages on Niles Blvd.
3. Easement and title report for public service easement along miles Blvd.

Air Quality and Noise Update 11/10/2020 Illingworth&Rodkin, inc
Parking Analysis 09/18/2020 Complete
Arborist Report Update 08/01/2020 Complete
Historical Review Studies 07/06/2020 Complete
Civil Engineer to complete all responses for resubmit 05/04/2020 Complete
Traffic Studies 08/02/2019 Complete
Submit formal permit application to City of Fremont 06/26/2019

 

 